AMAK project
Client: NIOC


Location :
Ahwaz – South of Iran

Project description :

  • Implementation of constructional and erection works of the facilities for the gathering and sweetening of 240 MMSCFD of associated gas comprising of :

    • 7compressor stations and associated dehydration plant.

    • 1 gas sweetening plant and associated acid gas compressor station.

    • 280 km of gas transfer pipelines

    • 90 km of 38kV and 11kV of power transfer lines.

Scope of work :

  • Material supply (partial) and execution of civil, concrete structure, steel structure, building, equipment installation, piping, electrical, instrumentation, insulation and painting and commissioning works.

Duration of work  : 34 months

Completion Date  : In progress

 