Location: Tabriz –
North-West Iran
Project description:
- Mechanical and
underground piping works of offsite area.
- Steel
structure, piping and electrical works of
LL/HDPE and B1 plant with a capacity of 100,000 tons/year polyethylene
and 7000 tons/year Botene.
Scope of work:
- Executions of
mechanical, piping, steel structure and associated civil works, insulation and
painting works, pre-commissioning and commissioning.
- Execution of
underground piping and associated civil works.
Duration of work : 29 months
Completion date : March, 1997