LL/HDPE and offsite area of Tabriz petrochemical complex
Client: NPC


Location:
Tabriz – North-West Iran

Project description:

  • Mechanical and underground piping works of offsite area.
  • Steel structure, piping and electrical works of  LL/HDPE and B1 plant with a capacity of 100,000 tons/year polyethylene and 7000 tons/year Botene.

Scope of work:

  • Executions of mechanical, piping, steel structure and associated civil works, insulation and painting works, pre-commissioning and commissioning.
  • Execution of underground piping and associated civil works.

Duration of work : 29 months

Completion date : March, 1997